Proj. No.

Projects

Description

Manager
6002 12th Street W. – Sidewalk Gunnery to Sunshine Blvd. 07/21/09 – Construction Substantially Complete Sarah Clarke
4083 A & W Bulb Improvements   Rob Phelan
  Airport Haul Road 06/16/10 – permits submitted and pending Betsie Hiatt
5034 Alico Rd. Connector Alignment Study. 06/16/10 – No Change,  BOCC adopted the alignment late September 2009 Sarah Clarke
4030 Alico Rd. Ditch Right of Way 04/20/10 - No Change, Purchasing Right of Way Don DeBerry
4030 Alico Road 6-Laning 01/29/09 - Processing Resolution of necessity for specific properties. Buying ROW Don DeBerry
4030 Alico Rd. / Pennsylvania St. Connector & Signal 12/17/09 -Construction completed Don DeBerry
6047 Boca Grande Drainage.    04/15/08 - Construction completed. Eyra Cash
4044 Bonita Beach Road — Phase II. 06/15/10 – No change, 100% plans complete, project ready for construction Eyra Cash
6002 Bonita Beach Road Sidewalk 09/16/08 - Construction completed. Eyra Cash
6002 Bonita Beach Road Sidewalk from Bonita Grande to I-75   Eyra Cash
4044 Bonita Beach Road – US 41 to Old US 41 Phase III.     06/15/10 - No Change, Working on 90% plans, preparing response to 1st RAI. Eyra Cash
0700 Brantley Rd. – US 41 to Summerlin – canal barrier system. 04/20/10 – Construction completed. Sarah Clarke
4030 Briarcliff Canal Filter Marsh. 06/16/10 - Construction complete – monitoring and maintenance ongoing. Betsie Hiatt
6002 Buckingham Rd. Paved Shoulders.
Phase I (SR82 to Neal Rd.) and
Phase II (Neal Rd. to Gunnery)
6/17/10 –  Phase I complete. Phase II bid documents prepared and to contacts to advertise for bids. Sarah Clarke
4088 Burnt Store Widening.    06/15/10 – (received 60% plans) SFWM permit application approved in Nov.. 30% ROW plans complete. Mike Rigsby
4020 Business 41 from Marianna to Littleton Rd.   Don DeBerry
5033 Cape Coral Parkway / Del Prado Turn Lane 04/21/09 - Project substantially complete.
Schedule punch list site visit.
 
Rob Phelan
4683 Captiva Drive CCCL Permit. 06/16/10 – Dune restoration complete –monitoring and maintenance ongoing. Betsie Hiatt
6713 Coconut Road Widening West of US 41   Rob Phelan
0700 College Parkway Drainage   Sarah Clarke
4054 Colonial Blvd. from I-75 to SR 82, 4 Lane to 6 Lane.                 06/15/10 – No Change Construction started Aug. 3.  Under Construction. Mike Rigsby
5054 Colonial Blvd. / McGregor to I - 75. 06/16/10 – Project suspended until the 2035 LRTP update is complete; December 2010. Sarah Clarke
6064 Colonial Blvd. / Metro Pkwy. Queue Jump. 04/20/10 – No Change, 60% plans on shelf Sarah Clarke
  Colonial initiative 04/20/10 – Value Engineering, Public Involvement under way Don DeBerry
4723 Corkscrew Road CRSA 12/17/09 - Advertised for CM selection Sarah Clarke will manage construction with Randy Cerchie. Don DeBerry
  Corkscrew Road Curve 06/16/10 -  Wood stork mitigation  - complete, maintenance ongoing Betsie Hiatt
0700 Corkscrew Road Curve.    01/29/09 - Construction Completed. Eyra Cash
  Corkscrew Road Panther Fencing 06/16/10 - complete, large female panther photographed in crossing. SR 82 culvert / fencing pending. Betsie Hiatt
4723 Corkscrew Road. Safety Improvements 6/17/10 – Construction Management firm selected; contract negotiation underway. Sarah Clarke
4078 CR 951 Extension. 04/20/10 - EIS withdrawn from Federal Highway. Voluntary right of way acquisition for county adopted alignment Don DeBerry
6713 Crystal Drive/Plantation Road Roundabout 6/16/10 – Design services proposal submitted and is being processed for approval. Sarah Clarke
4083 Cutlass Drive. 04/21/03/31/09 Rob Phelan
TBD Daniel Parkway 4 Lane Widening. 04/21/09 - No change, Collecting available data on project Rob Phelan
6713 Daniels Pkwy & Bell Tower Dr. 06/15/10 –  Stimulus Project – Stimulus Project – Roadway and signal work is complete. Both dual lefts are open to traffic. Working to complete sidewalk. Lora Celec
6713 Daniels Pkwy. / Treeline Av. Dual Left-Turn Lane.   

09/16/07 –  Construction Completed.

Eyra Cash
  Daniels Pkwy. Fire Station 06/16/10 – Permits finalized - 0.47 credits at Island Park Betsie Hiatt
5072 Daniel Pkwy. Widening 04/20/10 -  60% plans pending Don DeBerry
6713 Del Prado / Cape Coral Pkwy Turn Lane 03/17/09 - Waiting for Mast Arm installation Rob Phelan
6742 Del Prado Blvd. Median Improvements. 11/16/09 – Construction Completed. Eyra Cash
5066 Duke Highway   Randy Cerchie
  EOC 06/16/10 - In permitting, Corps contract approved Betsie Hiatt
5067 Estero Blvd Phase 1      06/16/10 - • ROW survey completed (4/21/2010) Surveyor have CD and 11x17 maps.
• Meet with Town to discuss potential small scale improvement location, working on cost estimate for improvements, Town to identified 1 additional location.
• Coordinating Meeting with Town, LeeDOT, LCU regarding Utility relocations.
Rob Phelan
  Estero Parkway Extension East of Ben Hill Griffin   Rob Phelan
5021 Estero River Flow Way Restoration 06/16/10 - Monitoring and maintenance ongoing. Betsie Hiatt
0700 Evans Connector – Metro Pkwy. to Evans Ave. 11/18/08 –  Draft report received and is under review. Sarah Clarke
4043 Gator Hole Preserve Tortoise Relocation. 06/16/10 – Initial land management for Phase 2 (80 acres) complete. FWC relocation permit submitted and pending final review of soils and financial assurance. Alico / Pennslvania tortoise relocation complete. Betsie Hiatt
4060
4081
4083 Gladiolus Drive 4-Laning from Winkler to Pine Ridge Road including A&W Bulb Road and Bass Road Widening 06/16/10 -• NTP 6-9-2008 – Underconstruction - Construction completion anticipated – July 2010.
• Adding Solar Powered Flashing Pedestrian lights at Mid-Block Cross-Walks
• Adding “Sharrows” and reduced speed limits in Harlem Heights area
• LCU meeting with M&S to discuss M&S revision to waterline alignment Thursday 6/17/2010. M&S indicated they should begin water line installation for A&W Bulb Road week of 6/21/2010
• Submitted RAI 1 for A&W Bulb Road permit on 6/4/2010
• Sending A&W plans to Operations and Traffic for review week of 6/21/2010
Rob Phelan
6002 Glenwood Ave sidewalk (Ortiz to Prospect) & Tice St (Ortiz to Lexington) 09/16/08 – Construction Completed. Eyra Cash
4055 Gunnery Road      Under construction Nicole Maxey
6002 Gunnery Sidewalk – Lehigh HS to Buckingham Rd. 09/16/08 – Construction Completed Sarah Clarke
5721 Hancock Bridge Pkwy./Pondella Rd. Alignment Study 6/16/10 – finalizing engineering report to recommend Pondella rather than Hancock. Alignment to be determined when funding available. Sarah Clarke
6002 Hancock Bridge Parkway 06/16/10 - Preparing plans paved shoulders – Orange Grove Blvd to 24th Rob Phelan
  Harbor Drive 06/16/10 – road extension complete Betsie Hiatt
4083 Hidden Lakes Mitigation Area. 06/16/10 – Exotic Maintenance and monitoring ongoing. “Sign-off” pending for Phase 1 mitigation area. Betsie Hiatt
6713 Homestead & Milwaukee Turn Lane. 11/16/09 - Construction Complete. As-built survey is complete and has been submitted to FDOT. Lora Celec
5063 Homestead Rd. – South of Sunrise to Alabama.    06/16/10 – No Change, SFWMD permit approved. Partial right-of-way acquisition underway with limited funds. Construction is not yet funded. Sarah Clarke
6713 Homestead Rd. & Beth Stacey Blvd. 03/18/08 -Construction of roadway and signal completed. Lora Celec
6002 Homestead Rd. Sidewalk/Bikepath. 

06/06/16/10 – Proposal received; negotiation underway.

Sarah Clarke
6002 Human Services – Harlem Heights Bus Shelters 06/16/10 - • Harlem Heights – Bus Shelter Plans for Harlem Heights.
• 2009-2010 projects - Page Park, Palmona Park and Charleston Park sidewalk out for construction. Support as required.
• 2010-2011 projects - Pine Manor – To review preliminary locations identified for 2010-2011 plans
• 2010-2015 projects - Meeting with Human Service to discuss planning for future sidewalk locations (2-5 year plan).
Rob Phelan
6002 Human Services Sidewalks – 2009-2010 projects 04/20/10 - • Page Park, Palmona Park and Charleston Park sidewalk plans completed and out for construction. Support as required. Rob Phelan
6002 Human Services Sidewalks – 2010-2011 projects 04/20/10 - • Pine Manor – To review preliminary locations identified for 2010-2011 plans Rob Phelan
4723 Imperial Marsh Preserve Wetland and Panther Mitigation Area Corkscrew Mitigation. 06/16/10 – No change Exotic Maintenance and monitoring ongoing. Betsie Hiatt
4060 Imperial Street 4-Laning from Bonita Beach Road to E. Terry Street Under Construction Nicole Maxey
8546 Island Park Addition 06/16/10 – No Change -  Purchase Contract denied Betsie Hiatt
8546 Island Park Regional Mitigation Project (North and South).    06/16/10 - Construction for North and South Phases complete. Monitoring and maintenance ongoing. Additional contract needed for South Phase maintenance. Betsie Hiatt
6674 Joel Blvd. at Country Club - Left turn lane. 06/16/10 – Project completed. Sarah Clarke
6713 Lee Blvd. & Leonard Blvd. 04/15/09 – U-Turn location shown on Concept Plans from Traffic at Driveway location of proposed City of Fort Myers development. Recommend not progressing this project. Rob Phelan
6713 Lee Blvd. / Sunshine Blvd. Turn Lanes.  06/15/10 - No Change, Under Construction Eyra Cash
6713 Leland Heights Blvd. / Lee Blvd. 06/16/10 - No change, Preparing preliminary design for minor intersection improvements Rob Phelan
0700 Littleton Extension. 04/15/08 – Project completed. Sarah Clarke
6002 Littleton Sidewalk—Old 41 to US 41. 06/15/10 - No Change,  Under Construction Eyra Cash
5060 Luckett / Sunshine Blvd. Corridor Extension Studies. 06/16/10 – No Change, Final report complete. Sarah Clarke
5714 Master Bridge   Ehab Guirguis
  Mitigation Bank Permit

06/16/10 – application nearly complete / submittal pending Corps guidance.

Betsie Hiatt
5904 Matlacha Bridge Replacement. 04/20/10 - Plans Complete. Award to BoCC 5/18/2010 Don DeBerry
  Matlacha / Snook Inn bat houses 06/16/10 - DEP permit issued. Bat houses complete and ready to be installed. Betsie Hiatt
0700 N. Airport Rd. Extension. 06/16/10 – No Change, Discussion with developer have resumed. Agreement is under review. Sarah Clarke
  Neal Rd. paved shoulders 04/20/10 - No change, 100% plans in house. Don DeBerry
4007 Orchid Isles ROMA. 06/16/10 - No change, Evaluation phase. Betsie Hiatt
  Oriole Road.  04/21/10 - DOS2008-00010, equivalent to 60 percent plans, is approved with stipulations. Right-of-way dedication has not occurred. Construction clearing and grubbing has started. Administration performed by developer. Andy Getch
4072 Ortiz Avenue 4-Laning from SR 82 to SR 80 (Luckett Road).   06/15/10 - No change, SFWMD permit approved, & working on 100% plans. Eyra Cash
  Ospreys / Sanibel Causeway 06/16/10 – poles installed / nest relocation pending  
4007 Panther Fencing. 7/15/08 – No change, Completed. Large female panther photographed in crossing. Betsie Hiatt
4007 Panther Mitigation Area (Sec. 33). 06/16/10 –  Construction contract and Utilities agreement pending. Betsie Hiatt
5722 Persimmon Ridge Bridge 12/17/09 - Construction Complete Don DeBerry
4007 Pine Ridge Facility. 06/16/10 – No change, in permitting / 2.13 mitigation credits will be provided at Island Park Betsie Hiatt
4065 Plantation Extension from Idlewild to Colonial Blvd.      11/16/09 - Construction Complete
Opened Nov. 13
Mike Rigsby
TBD Pondella Medians. 06/16/10 – No Change, Looking at median locations for Pondella Road. Rob Phelan
  Red Sox Facility 06/16/10 – Permits issued, 1.8 credits at Island Park Betsie Hiatt
6024 Roadway Beautification Projects   Pat Moore
4084 Sandy Lane Design. 04/21/10 - Project is not funded in the current CIP

Andy Getch

4084 Sandy Lane Extension 03/16/09 - No change, Project is not funded in the current CIP Andy Getch
  Sanibel Causeway 06/16/10 - permit issued for permit modification / mitigation requirement. Betsie Hiatt
TBD Sanibel Causeway U-Turn 04/21/09 - • U-turn east of Toll Plaza incorporated into TYLin Plans to be included in Stimulus plans at Toll Plaza. Rob Phelan
4604 Six Mile Cypress Parkway 06/16/10 -
• Bids Due 6/16/2010
• LCU relocating water/sewer lines. City of Fort Myers advertising water line adjustments
Rob Phelan
6002 Six Mile Cypress Pathway – Daniels to Metro Pkwy.     07/21/09 – Construction Complete Sarah Clarke
6002 Six Mile Cypress Pathway – Metro to US 41. 07/21/09 – Construction Complete Sarah Clarke
6713 Six Mile Cypress Pkwy. & Independence Circle W. 08/18/09 –  Construction is complete. Lora Celec
  Slater Rd. paved shoulders 04/20/10 - 90% plans in house Don DeBerry
6002 Slater Rd. – sidewalk Bayshore to Del Prado Blvd. 04/20/10 – Construction Complete Sarah Clarke
5064 SR 82 / Daniels Dual Left-Turn Lane. 05/19/09 –  Construction Completed. Eyra Cash
6002 Stringfellow Rd.  Sidewalk – 1st Ave. to York Rd. 06/15/10 – No Change, Design in house Eyra Cash
6007 Summerlin Rd. – Cypress Lake to
Boy Scout Drive.     
06/16/10 – No Change, Under construction. Sarah Clarke

4067

 
Summerlin Road Sidewalk  from
San Carlos Blvd. to Gladiolus Dr.
06/15/10 - 90% complete, being revised .
 
Mike Rigsby
4067 Summerlin Road Sidewalk from Lakewood to Gladiolus Dr. 11/16/09 - Construction Complete Eyra Cash
4604 Sunniland Blvd – Lee Blvd to Park St. 06/16/10 - No Change, Updating Plans for potential ARRA Stimulus Funding. Rob Phelan
6713 Sunshine Blvd. & 12th St. West 12/17/09 - Construction Completed. Rob Phelan
6002 Texas Rd. – sidewalk Leeland Hgts. To Davis. 07/21/09 – Construction Completed. Sarah Clarke
4053 Three Oaks North from Alico to Airport Ditch (Source, Inc.).    04/21/10 - Project is substantially complete for construction under DOS2005-00314. Administration performed by developer. Contractor is addressing punch list items. Andy Getch
  Three Oaks Park Rehab. 04/20/10 - No change, Under Construction. Don DeBerry
4053 Three Oaks Parkway From
Alico Canal to Daniels Parkway
06/15/10 - No Change, Consultant submitted RAI to SFWMD, working on 90% plans. Eyra Cash
4043 Three Oaks Parkway South from Brooks to E. Terry Street   Under Construction. Nicole Maxey
4081 Three Oaks Parkway Widening from Corkscrew to Alico Rd.     Under Construction. Nicole Maxey
4081/
5021
Three Oaks Widening and Estero Pkwy Wetland Mitigation Under Construction. Betsie Hiatt
6002 Tice St. – sidewalk Ortiz to Lexington.  04/15/08 –  No change – construction nearing completion. Sarah Clarke
6002 Tice St. – sidewalk Waverly to Ortiz. 04/15/08 – Record plans received. Project Completed. Sarah Clarke
  Treeline Ave 02/02/09 - Drafting Technical assistance letter for panther signs and speed limits. Betsie Hiatt
TBD Veteran’s Pkwy. Merge lane at Santa Barbara 04/21/09 • Provided sketch, estimate and issues with merge lane to Scott. It is to be discussed at COCC TAC meeting 1/29/09. Rob Phelan
5020 Veteran's Pkwy. Mitigation Area. 06/16/10 – Deed to state DEP pending BoCC approval. Final exotic removal complete. Betsie Hiatt
5029 Veteran's Pkwy. Ramp 04/15/08 – Construction Completed. Sarah Clarke
Misc. Veterans Pkwy Right of Way 06/16/10 - • Researching for ROW information  for Cooner & Associates Rob Phelan
  Veteran's / Surfside Intersection   Don DeBerry
6755 Veterans Pkwy./Santa Barbara Overpass 6/16/10 – Design project kick off held June 3, 2010. Sarah Clarke
4007 Wake / Hatchee 6/16/10 – Permitting complete Betsie Hiatt
4007 Wild Turkey Strand Wetlands and Panther Mitigation Area 06/16/10 – In permitting. Additional topo pending. Ditch crossing permit issued for P&R. Betsie Hiatt
6675 Williams Rd. at 5th St. – left turn lane. 11/17/09 – No Change, Under Construction. Sarah Clarke
6002 Williams Road Sidewalk.    05/19/09 –  Construction Completed. Eyra Cash
Misc. Winker Road / College Parkway – ROW Vacation 06/16/10 - • Working with utilities to identify (LCU / Embarq) to identify objection to ROW vacation
• Partial vacation of Zipperer deed by applicant completed.
Rob Phelan
 
Elderberry Lane. 08/18/09 - Road open Mike Rigsby
  MSBU – San Carlos Dr. 6/16/10 – San Carlos Dr. project under construction. Sarah Clarke
MSBU – Western Acres, Harbor Dr., Homestead Ln., San Carlos Dr. 4/20/10 – San Carlos Dr. project under construction. Sarah Clarke
Roundabouts on Sunshine & 23rd . 04/20/10 - No Change, 8th St needs right of way Don DeBerry
Advertise:
951 / Golf Course Maintenance Swap 01/29/09 - Ranking approved by BoCC 4/15/2008 will begin negotiating contracts. Don DeBerry
Orange River Paved Shoulders 04/20/10 - No Change, 100% plans in house Don DeBerry
Palmetto Ridge Bridge Replacement  01/29/09 - Selected consultants. Don DeBerry