|
Proj. No. |
Projects |
Description |
Manager |
|
6002 |
12th
Street W. Sidewalk Gunnery to Sunshine Blvd. |
07/21/09
Construction Substantially Complete |
Sarah
Clarke |
|
4083 |
A & W Bulb Improvements |
|
Rob Phelan |
|
5034 |
Alico Rd. Connector
Alignment Study. |
11/17/09 BOCC
adopted the alignment late September 2009 |
Sarah
Clarke |
|
4030 |
Alico Rd. Ditch Right of
Way |
08/18/09 -
No Change, Purchasing Right of Way |
Don
DeBerry |
|
4030 |
Alico Road 6-Laning |
01/29/09 - Processing Resolution of necessity
for specific properties. Buying ROW |
Don
DeBerry |
|
4030 |
Alico Rd. / Pennsylvania
St. Connector & Signal |
12/17/09 -Construction completed |
Don
DeBerry |
|
6002 |
Arthur Sidewalk |
|
Randy Cerchie |
|
6047 |
Boca Grande Drainage.
 |
04/15/08 - Construction completed. |
Eyra Cash |
|
4044 |
Bonita Beach Road Phase II. |
12/17/09 No change, 100% plans complete, project ready
for construction |
Eyra Cash |
|
6002 |
Bonita Beach Road Sidewalk |
09/16/08 - Construction completed. |
Eyra Cash |
|
6002 |
Bonita Beach Road Sidewalk
from Bonita Grande to I-75 |
|
Eyra Cash |
|
4044 |
Bonita Beach Road US 41
to Old US 41 Phase III.
 |
11/16/09 - No change, 60%
plans complete working of the submittal to
SFWMD. |
Eyra Cash |
|
0700 |
Brantley Rd. US 41 to
Summerlin canal barrier system. |
11/17/09 No change, Under Construction |
Sarah
Clarke |
|
4030 |
Briarcliff Canal Filter
Marsh. |
02/02/09 - Construction underway and nearly
complete pending perimeter fencing and marsh
plantings. |
Betsie
Hiatt |
|
6002 |
Buckingham Rd. Paved
Shoulders. |
11/17/09 Bids opened, contract award on
11/17/09 BOCC agenda. Preconstruction meeting
scheduled for 11/30/09. Construction to begin
in December. |
Sarah
Clarke |
|
4088 |
Burnt
Store Widening.
 |
12/16/09 SFWM permit
application approved in Nov, 2009 - 30% ROW plans complete. |
Mike
Rigsby |
|
4020 |
Business 41 from Marianna
to Littleton Rd. |
|
Don
DeBerry |
|
5033 |
Cape Coral Parkway / Del
Prado Turn Lane |
04/21/09 - Project substantially complete.
Schedule punch list site visit.
|
Rob Phelan |
|
5815 |
Cape Coral Toll |
|
Paul
Wingard |
|
4683 |
Captiva Drive CCCL Permit. |
02/02/09 Dune restoration complete
monitoring and maintenance ongoing. |
Betsie
Hiatt |
|
6713 |
Coconut Road Widening West
of US 41 |
|
Rob Phelan |
|
0700 |
College Parkway Drainage |
|
Sarah
Clarke |
|
4054 |
Colonial
Blvd. from I-75 to SR 82, 4 Lane to 6 Lane.
 |
11/16/09 Construction started Aug. 3. Under
Construction. |
Mike
Rigsby |
|
5054 |
Colonial Blvd. / McGregor
to I - 75. |
08/18/09 No Change, Final IOAR submitted 7/10/09. Once
FDOT/FHWA approve, the Project development
summary report (PDSR) and Environmental
Assessment (EA) will be submitted for review.
Expect to hold public hearing late 2009. |
Sarah
Clarke |
|
6064 |
Colonial Blvd. / Metro
Pkwy. Queue Jump. |
11/17/09 60% plans on shelf |
Sarah
Clarke |
|
|
Colonial initiative |
04/15/08
Construction
Completed |
Eyra Cash |
|
4723 |
Corkscrew Road CRSA |
12/17/09 - No Change, ongoing |
Don
DeBerry |
|
0700 |
Corkscrew Road Curve.
 |
01/29/09 - Construction Completed. |
Eyra Cash |
|
4078 |
CR 951 Extension. |
12/17/09 - No Change, Draft EIS sent
to Federal Highway. Voluntary right of way
acquisition underway. |
Don
DeBerry |
|
4083 |
Cutlass Drive. |
04/21/03/31/09 |
Rob Phelan |
|
|
Daniels Fire Station |
7/15/08 Permits finalized - 0.47 credits at
Island Park Panther Fencing complete, large
female panther photographed in crossing |
Betsie
Hiatt |
|
TBD |
Daniel Parkway 4 Lane
Widening. |
04/21/09 - No change, Collecting available data on
project |
Rob Phelan |
|
6713 |
Daniels Pkwy. / Treeline
Av. Dual Left-Turn Lane.
 |
09/16/07 Construction
Completed. |
Eyra Cash |
|
6713 |
Daniels Pkwy & Bell Tower
Dr. |
12/16/09 Stimulus Project Better
Roads was low bidder. Bid to be awarded by the
Board in January. |
Lora Celec |
|
6713 |
Del Prado / Cape Coral Pkwy
Turn Lane |
03/17/09 - Waiting for Mast Arm installation |
Rob Phelan |
|
6742 |
Del Prado Blvd. Median
Improvements. |
11/16/09 Construction Completed. |
Eyra Cash |
|
5066 |
Duke Highway |
|
Randy Cerchie |
|
5067 |
Estero Blvd Phase 1
 |
12/17/09 - ROW survey underway
Town Council provided list of small scale
projects, may be able to incorporate some bus
pull off with resurfacing project.
Coordinating Meeting with Town, LeeDOT, LCU
regarding Utility relocations |
Rob Phelan |
|
|
Estero Parkway Extension
East of Ben Hill Griffin |
|
Rob Phelan |
|
5021 |
Estero River Flow Way Restoration |
02/02/09 - Monitoring and maintenance ongoing. |
Betsie
Hiatt |
|
0700 |
Evans Connector Metro
Pkwy. to Evans Ave. |
11/18/08 Draft report received and is
under review. |
Sarah
Clarke |
|
4043 |
Gator Hole Preserve
Tortoise Relocation. |
02/02/09 Initial land management for Phase 2
(80 acres) complete. Initiating contracts for FWC relocation site permit. Alico /
Pennsylvania tortoise relocation complete. |
Betsie
Hiatt |
|
4060 |
|
4081 |
|
4083 |
Gladiolus Drive 4-Laning from Winkler to Pine
Ridge Road including A&W Bulb Road and Bass
Road Widening |
12/17/09 No change, NTP 6-9-2008 under construction.
Traffic on north side lanes as of 8/17/09
Contractor working on south side
Working with Dave Douglas for A&W Bulb Road
permit package
Rev. 2, 3 & 4 issued
Reviewing driveways on south side of roadway
through Harlem Heights |
Rob Phelan |
|
6002 |
Glenwood
Ave sidewalk (Ortiz to Prospect) & Tice St
(Ortiz to Lexington) |
09/16/08 Construction Completed. |
Eyra Cash |
|
4055 |
Gunnery Road
 |
Under construction |
Nicole Maxey |
|
6002 |
Gunnery Sidewalk Lehigh
HS to Buckingham Rd. |
09/16/08 Construction Completed |
Sarah
Clarke |
|
5721 |
Hancock Bridge Extension |
08/18/09 No Change, Analyzing engineering and economic
data. Second public workshop to be held fall
2009. |
Sarah
Clarke |
|
4083 |
Hidden Lakes Mitigation
Area. |
02/02/09 No change,
Exotic Maintenance and monitoring ongoing. |
Betsie
Hiatt |
|
6713 |
Homestead & Milwaukee Turn
Lane. |
11/16/09, (Westbound left turn lane on
Milwaukee Blvd.) Stimulus Project
Construction Complete. As-built survey is
complete but has not been submitted to FDOT. |
Lora Celec |
|
5063 |
Homestead
Rd. South of Sunrise to Alabama.
 |
11/17/09 SFWMD permit approved. Partial
right-of-way acquisition underway with limited
funds. Construction is not yet funded. |
Sarah
Clarke |
|
6713 |
Homestead Rd. & Beth Stacey
Blvd. |
03/18/08 -Construction of roadway and signal
completed. |
Lora Celec |
|
6002 |
Homestead Rd. Sidewalk. |
08/18/09 No Change Project has been
submitted as a candidate for enhancement
stimulus funding. |
Sarah
Clarke |
|
4723 |
Imperial Marsh Preserve
Wetland and Panther Mitigation Area Corkscrew
Mitigation. |
02/02/09 No change Exotic
Maintenance and monitoring ongoing. |
Betsie
Hiatt |
|
4060 |
Imperial Street 4-Laning
from Bonita Beach Road to E. Terry Street  |
Under Construction |
Nicole Maxey |
|
8546 |
Island Park Addition |
02/02/09 Purchase Contract denied
Wake / Hatchee in permitting. |
Betsie
Hiatt |
|
8546 |
Island
Park Regional Mitigation Project (North and
South).
 |
02/02/09 - No change (North and South)- North Phase
Completed. South Phase Complete. Monitoring and
maintenance ongoing. |
Betsie
Hiatt |
|
6674 |
Joel Blvd. at Country Club
- Left turn lane. |
11/17/09 Construction underway; delayed
pending relocation of a FGUA waterline. |
Sarah
Clarke |
|
6713 |
Lee Blvd. & Leonard Blvd. |
04/15/09 U-Turn location
shown on Concept Plans from Traffic at
Driveway location of proposed City of Fort
Myers development. Recommend not progressing
this project. |
Rob Phelan |
|
6713 |
Lee Blvd. / Sunshine Blvd.
Turn Lanes. |
12/17/09 -Tentative NTP
January 11, 2010 |
Eyra Cash |
|
6713 |
Leland Heights Blvd. / Lee
Blvd. |
12/17/09 - No change, Preparing
preliminary design for minor intersection
improvements |
Rob Phelan |
|
0700 |
Littleton Extension. |
04/15/08 Project completed. |
Sarah
Clarke |
|
6002 |
Littleton SidewalkOld 41
to US 41. |
11/16/09 - Schedule for Bid January 20, 2010 |
Eyra Cash |
|
5060 |
Luckett / Sunshine Blvd.
Corridor Extension Studies. |
11/17/09 No Change, Final report complete. |
Sarah
Clarke |
|
5714 |
Master Bridge |
|
Ehab Guirguis |
|
5904 |
Matlacha Bridge
Replacement. |
12/17/09 - plans complete.
Advertised for bids 9/18/2009 |
Don
DeBerry |
|
0700 |
N. Airport Rd. Extension. |
11/17/09 Discussion with developer have
resumed. Agreement is under review. |
Sarah
Clarke |
|
|
Neal Rd. paved shoulders
|
12/17/2009 - 100% plans in
house |
|
|
4007 |
Orchid Isles ROMA. |
02/02/09 - No change,
Evaluation phase. |
Betsie
Hiatt |
|
|
Oriole Road.
 |
03/16/09 - No change - DOS2008-00010, equivalent to
60 percent plans, is under review. |
Andy Getch |
|
4072 |
Ortiz Avenue 4-Laning from SR 82 to SR 80
(Luckett Road).
 |
12/17/09 - No change, SFWMD permit approved, & working on
100% plans |
Eyra Cash |
|
4007 |
Panther Fencing. |
7/15/08 No change -
Completed. Large female panther photographed
in crossing. |
Betsie
Hiatt |
|
4007 |
Panther Mitigation Area
(Sec. 33). |
02/02/09 Incorporated in to Colonial
Widening permit application. |
Betsie
Hiatt |
|
5722 |
Persimmon Ridge Bridge |
12/17/2009 - Construction Complete |
Don
DeBerry |
|
4007 |
Pine Ridge Facility. |
02/02/09 No change - in permitting /
2.13 mitigation credits will be provided at
Island Park |
Betsie
Hiatt |
|
4065 |
Plantation
Extension from Idlewild to Colonial Blvd.
 |
11/16/09 - Construction Complete
Opened
Nov. 13 |
Mike
Rigsby |
|
TBD |
Pondella Medians. |
12/17/09 No Change - Looking at median locations for
Pondella Road. |
Rob Phelan |
|
6024 |
Roadway Beautification
Projects |
|
Pat Moore |
|
4084 |
Sandy Lane Design. |
06/12/09 Corridor Evaluation Study
complete by Cella & Associates and adopted by
BoCC in November 2004. Project is on hold
pending funding. |
Andy Getch
|
|
4084 |
Sandy Lane Extension |
03/16/09 -
No change - Project is not funded in the
current CIP |
Andy Getch |
|
|
Sanibel Causeway |
02/02/09 - Drafting permit applications for
permit modification / mitigation requirement. |
Betsie
Hiatt |
|
TBD |
Sanibel Causeway U-Turn |
04/21/09 - U-turn east of Toll Plaza
incorporated into TYLin Plans to be included
in Stimulus plans at Toll Plaza. |
Rob Phelan |
|
4604 |
Six Mile Cypress Parkway |
12/17/09 - ARRA Stimulus Project
Public Hearing held 11/10/09
Preparing Re-Submission to FDOT prior to
Christmas
If approval from FDOT received anticipating
bidding in January 2010
Working on DO package |
Rob Phelan |
|
6002 |
Six Mile Cypress Pathway
Daniels to Metro Pkwy.  |
07/21/09 Construction Complete |
Sarah
Clarke |
|
6002 |
Six Mile Cypress Pathway
Metro to US 41. |
07/21/09 Construction Complete |
Sarah
Clarke |
|
6713 |
Six Mile Cypress Pkwy. &
Independence Circle W. |
08/18/09 Construction is complete. |
Lora Celec |
|
|
Slater Rd. paved shoulders
|
12/17/2009 - holding for county maintained
right of way survey |
|
|
6002 |
Slater Rd. sidewalk
Bayshore to Del Prado Blvd. |
11/17/09 No Change, Under Construction |
Sarah
Clarke |
|
5064 |
SR 82 / Daniels Dual
Left-Turn Lane. |
05/19/09 Construction Completed. |
Eyra Cash |
|
6002 |
Stringfellow Rd.
Sidewalk 1st Ave. to York Rd. |
12/17/09 Requested survey, design in house ~
Design by December 31 |
Eyra Cash |
|
6007 |
Summerlin Rd. Cypress
Lake to
Boy Scout Drive.
 |
11/17/09 No Change, Under construction. |
Sarah
Clarke |
4067
|
Summerlin Road Sidewalk from
San Carlos Blvd. to Gladiolus Dr.  |
12/16/09 -
No Change,
Summerlin Road Sidewalk - 90% complete, in
review.
|
Mike
Rigsby |
|
4067 |
Summerlin Road Sidewalk
from Lakewood to Gladiolus Dr. |
11/16/09 - Construction Complete |
Eyra Cash |
|
4604 |
Sunniland Blvd Lee Blvd
to Park St. |
12/17/09 - No Change - Updating Plans for potential ARRA
Stimulus Funding. |
Rob Phelan |
|
6713 |
Sunshine Blvd. & 12th St. West |
12/17/09 - Construction Completed. |
Rob Phelan |
|
6002 |
Texas Rd. sidewalk
Leeland Hgts. To Davis. |
07/21/09 Construction Completed. |
Sarah
Clarke |
|
4053 |
Three
Oaks North from Alico to Airport Ditch
(Source, Inc.).
 |
02/02/09 - Consultant working on the SFWMD &
USACOE RAI. Project is under construction. |
Andy Getch |
|
|
Three Oaks Park Rehab. |
12/17/09 - No change, under Construction. |
Don
DeBerry |
|
4053 |
Three
Oaks Parkway From
Alico Canal to Daniels Parkway
 |
12/17/09
No Change,
Consultant received additional RAI from SFWMD
& waiting on ACOE RAI. 90% plans complete. |
Eyra Cash |
|
4043 |
Three Oaks Parkway South
from Brooks to E. Terry Street
 |
Under Construction. |
Nicole Maxey |
|
4081 |
Three Oaks Parkway Widening
from Corkscrew to Alico Rd.
 |
Under Construction. |
Nicole Maxey |
4081/
5021 |
Three Oaks Widening and
Estero Pkwy Wetland Mitigation |
Under Construction. |
Betsie
Hiatt |
|
6002 |
Tice St. sidewalk Ortiz
to Lexington. |
04/15/08 No change construction
nearing completion. |
Sarah
Clarke |
|
6002 |
Tice St. sidewalk Waverly
to Ortiz. |
04/15/08 Record plans received. Project
Completed. |
Sarah
Clarke |
|
|
Treeline Ave |
02/02/09 - Drafting Technical assistance
letter for panther signs and speed limits. |
Betsie
Hiatt |
|
TBD |
Veterans Pkwy. merge lane
at Santa Barbara |
04/21/09 Provided sketch, estimate and
issues with merge lane to Scott. It is to be
discussed at COCC TAC meeting 1/29/09. |
Rob Phelan |
|
5020 |
Veteran's Pkwy. Mitigation
Area. |
02/02/09 Deed to state DEP pending with
County Lands. Coordinating additional exotic
removal. |
Betsie
Hiatt |
|
5029 |
Veteran's Ramp. |
04/15/08 Substantially complete. |
Sarah
Clarke |
|
|
Veteran's / Surfside
Intersection |
|
Don
DeBerry |
|
4007 |
Wake / Hatchee |
7/15/08 No change - In permitting. |
Betsie
Hiatt |
|
4007 |
Wild Turkey Strand Wetlands
and Panther Mitigation Area |
02/02/09 In permitting. Drafting ditch
crossing permit applications for P&R. |
Betsie
Hiatt |
|
6675 |
Williams Rd. at 5th
St. left turn lane. |
11/17/09 No Change, Under Construction. |
Sarah
Clarke |
|
6002 |
Williams Road Sidewalk.
 |
05/19/09 Construction Completed. |
Eyra Cash |
|
|
|
|
|
|
|
|
|
Elderberry Lane. |
08/18/09 - Road open |
Mike
Rigsby |
|
|
MSBU Western Acres,
Harbor Dr., Homestead Ln., San Carlos Dr. |
11/17/09 Bids received, contract awarded.
Notice to proceed issued 11/9/09. |
Sarah
Clarke |
|
|
Roundabouts on Sunshine &
23rd . |
12/17/09 - 8th St
needs right of way |
Don
DeBerry |
|
|
|
|
|
|
Advertise: |
|
|
|
|
951 / Golf Course
Maintenance Swap |
01/29/09 - Ranking approved by BoCC 4/15/2008
will begin negotiating contracts. |
Don
DeBerry |
|
|
Orange River Paved
Shoulders |
12/17/2009 - 100% plans in house |
Don
DeBerry |
|
|
Palmetto Ridge Bridge
Replacement |
01/29/09 - Selected consultants. |
Don
DeBerry |
|
|
|
|
|