|
Proj. No. |
Projects |
Description |
Manager |
|
6002 |
12th
Street W. Sidewalk Gunnery to Sunshine Blvd. |
07/21/09
Construction Substantially Complete |
Sarah
Clarke |
|
4083 |
A & W Bulb Improvements |
|
Rob Phelan |
|
|
Airport Haul Road
|
06/16/10 permits
submitted and pending |
Betsie
Hiatt |
|
5034 |
Alico Rd. Connector
Alignment Study. |
06/16/10 No
Change, BOCC
adopted the alignment late September 2009 |
Sarah
Clarke |
|
4030 |
Alico Rd. Ditch Right of
Way |
04/20/10 -
No Change, Purchasing Right of Way |
Don
DeBerry |
|
4030 |
Alico Road 6-Laning |
01/29/09 - Processing Resolution of necessity
for specific properties. Buying ROW |
Don
DeBerry |
|
4030 |
Alico Rd. / Pennsylvania
St. Connector & Signal |
12/17/09 -Construction completed |
Don
DeBerry |
|
6047 |
Boca Grande Drainage.
 |
04/15/08 - Construction completed. |
Eyra Cash |
|
4044 |
Bonita Beach Road Phase II. |
06/15/10 No change, 100% plans complete, project ready
for construction |
Eyra Cash |
|
6002 |
Bonita Beach Road Sidewalk |
09/16/08 - Construction completed. |
Eyra Cash |
|
6002 |
Bonita Beach Road Sidewalk
from Bonita Grande to I-75 |
|
Eyra Cash |
|
4044 |
Bonita Beach Road US 41
to Old US 41 Phase III.
 |
06/15/10 - No Change, Working on 90% plans, preparing
response to 1st RAI. |
Eyra Cash |
|
0700 |
Brantley Rd. US 41 to
Summerlin canal barrier system. |
04/20/10 Construction completed. |
Sarah
Clarke |
|
4030 |
Briarcliff Canal Filter
Marsh. |
06/16/10 - Construction complete monitoring
and maintenance ongoing. |
Betsie
Hiatt |
|
6002 |
Buckingham Rd. Paved
Shoulders.
Phase I (SR82 to Neal Rd.) and
Phase II (Neal Rd. to Gunnery) |
6/17/10 Phase I complete. Phase
II bid documents prepared and to contacts to
advertise for bids. |
Sarah
Clarke |
|
4088 |
Burnt
Store Widening.
 |
06/15/10 (received 60% plans) SFWM permit
application approved in Nov.. 30% ROW plans
complete. |
Mike
Rigsby |
|
4020 |
Business 41 from Marianna
to Littleton Rd. |
|
Don
DeBerry |
|
5033 |
Cape Coral Parkway / Del
Prado Turn Lane |
04/21/09 - Project substantially complete.
Schedule punch list site visit.
|
Rob Phelan |
|
4683 |
Captiva Drive CCCL Permit. |
06/16/10 Dune restoration complete
monitoring and maintenance ongoing. |
Betsie
Hiatt |
|
6713 |
Coconut Road Widening West
of US 41 |
|
Rob Phelan |
|
0700 |
College Parkway Drainage |
|
Sarah
Clarke |
|
4054 |
Colonial
Blvd. from I-75 to SR 82, 4 Lane to 6 Lane.
 |
06/15/10 No Change Construction started Aug. 3. Under
Construction. |
Mike
Rigsby |
|
5054 |
Colonial Blvd. / McGregor
to I - 75. |
06/16/10 Project suspended until the 2035
LRTP update is complete; December 2010. |
Sarah
Clarke |
|
6064 |
Colonial Blvd. / Metro
Pkwy. Queue Jump. |
04/20/10 No Change, 60% plans on shelf |
Sarah
Clarke |
|
|
Colonial initiative |
04/20/10 Value Engineering, Public
Involvement under way |
Don
DeBerry |
|
4723 |
Corkscrew Road CRSA |
12/17/09 - Advertised for CM selection Sarah
Clarke will manage construction with Randy
Cerchie. |
Don
DeBerry |
|
|
Corkscrew Road Curve |
06/16/10 - Wood stork
mitigation - complete, maintenance ongoing |
Betsie
Hiatt |
|
0700 |
Corkscrew Road Curve.
 |
01/29/09 - Construction Completed. |
Eyra Cash |
|
|
Corkscrew Road Panther Fencing |
06/16/10 - complete, large female panther
photographed in crossing. SR 82 culvert /
fencing pending. |
Betsie
Hiatt |
|
4723 |
Corkscrew Road. Safety
Improvements |
6/17/10 Construction Management firm
selected; contract negotiation underway. |
Sarah
Clarke |
|
4078 |
CR 951 Extension. |
04/20/10 - EIS withdrawn
from Federal Highway. Voluntary right of way
acquisition for county adopted alignment |
Don
DeBerry |
|
6713 |
Crystal Drive/Plantation
Road Roundabout |
6/16/10 Design services
proposal submitted and is being processed for
approval. |
Sarah
Clarke |
|
4083 |
Cutlass Drive. |
04/21/03/31/09 |
Rob Phelan |
|
TBD |
Daniel Parkway 4 Lane
Widening. |
04/21/09 - No change, Collecting available data on
project |
Rob Phelan |
|
6713 |
Daniels Pkwy & Bell Tower
Dr. |
06/15/10
Stimulus
Project Stimulus Project Roadway and
signal work is complete. Both dual lefts are
open to traffic. Working to complete sidewalk. |
Lora Celec |
|
6713 |
Daniels Pkwy. / Treeline
Av. Dual Left-Turn Lane.
 |
09/16/07 Construction
Completed. |
Eyra Cash |
|
|
Daniels Pkwy. Fire Station |
06/16/10 Permits finalized - 0.47 credits at
Island Park |
Betsie
Hiatt |
|
5072 |
Daniel Pkwy. Widening |
04/20/10 -
60% plans pending |
Don
DeBerry |
|
6713 |
Del Prado / Cape Coral Pkwy
Turn Lane |
03/17/09 - Waiting for Mast Arm installation |
Rob Phelan |
|
6742 |
Del Prado Blvd. Median
Improvements. |
11/16/09 Construction Completed. |
Eyra Cash |
|
5066 |
Duke Highway |
|
Randy Cerchie |
|
|
EOC |
06/16/10 - In permitting, Corps contract
approved |
Betsie
Hiatt |
|
5067 |
Estero Blvd Phase 1
 |
06/16/10 - ROW survey completed (4/21/2010)
Surveyor have CD and 11x17 maps.
Meet with Town to discuss potential small
scale improvement location, working on cost
estimate for improvements, Town to identified
1 additional location.
Coordinating Meeting with Town, LeeDOT, LCU
regarding Utility relocations. |
Rob Phelan |
|
|
Estero Parkway Extension
East of Ben Hill Griffin |
|
Rob Phelan |
|
5021 |
Estero River Flow Way Restoration |
06/16/10 - Monitoring and maintenance ongoing. |
Betsie
Hiatt |
|
0700 |
Evans Connector Metro
Pkwy. to Evans Ave. |
11/18/08 Draft report received and is
under review. |
Sarah
Clarke |
|
4043 |
Gator Hole Preserve
Tortoise Relocation. |
06/16/10 Initial land management for Phase 2
(80 acres) complete. FWC relocation permit
submitted and pending final review of soils
and financial assurance. Alico / Pennslvania
tortoise relocation complete. |
Betsie
Hiatt |
|
4060 |
|
4081 |
|
4083 |
Gladiolus Drive 4-Laning from Winkler to Pine
Ridge Road including A&W Bulb Road and Bass
Road Widening |
06/16/10 - NTP 6-9-2008 Underconstruction -
Construction completion anticipated July
2010.
Adding Solar Powered Flashing Pedestrian
lights at Mid-Block Cross-Walks
Adding Sharrows and reduced speed limits
in Harlem Heights area
LCU meeting with M&S to discuss M&S revision
to waterline alignment Thursday 6/17/2010. M&S
indicated they should begin water line
installation for A&W Bulb Road week of
6/21/2010
Submitted RAI 1 for A&W Bulb Road permit on
6/4/2010
Sending A&W plans to Operations and Traffic
for review week of 6/21/2010 |
Rob Phelan |
|
6002 |
Glenwood
Ave sidewalk (Ortiz to Prospect) & Tice St
(Ortiz to Lexington) |
09/16/08 Construction Completed. |
Eyra Cash |
|
4055 |
Gunnery Road
 |
Under construction |
Nicole Maxey |
|
6002 |
Gunnery Sidewalk Lehigh
HS to Buckingham Rd. |
09/16/08 Construction Completed |
Sarah
Clarke |
|
5721 |
Hancock Bridge
Pkwy./Pondella Rd. Alignment Study |
6/16/10 finalizing engineering report to
recommend Pondella rather than Hancock.
Alignment to be determined when funding
available. |
Sarah
Clarke |
|
6002 |
Hancock Bridge Parkway |
06/16/10 - Preparing plans paved shoulders
Orange Grove Blvd to 24th |
Rob Phelan |
|
|
Harbor Drive |
06/16/10 road extension complete |
Betsie
Hiatt |
|
4083 |
Hidden Lakes Mitigation
Area. |
06/16/10 Exotic Maintenance and monitoring
ongoing. Sign-off pending for Phase 1
mitigation area. |
Betsie
Hiatt |
|
6713 |
Homestead & Milwaukee Turn
Lane. |
11/16/09 -
Construction Complete. As-built survey is
complete and has been submitted to FDOT. |
Lora Celec |
|
5063 |
Homestead
Rd. South of Sunrise to Alabama.
 |
06/16/10 No Change, SFWMD permit approved. Partial
right-of-way acquisition underway with limited
funds. Construction is not yet funded. |
Sarah
Clarke |
|
6713 |
Homestead Rd. & Beth Stacey
Blvd. |
03/18/08 -Construction of roadway and signal
completed. |
Lora Celec |
|
6002 |
Homestead Rd. Sidewalk/Bikepath. |
06/06/16/10 Proposal received; negotiation
underway. |
Sarah
Clarke |
|
6002 |
Human Services Harlem
Heights Bus Shelters |
06/16/10 - Harlem Heights Bus Shelter
Plans for Harlem Heights.
2009-2010 projects - Page Park, Palmona Park
and Charleston Park sidewalk out for
construction. Support as required.
2010-2011 projects - Pine Manor To review
preliminary locations identified for 2010-2011
plans
2010-2015 projects - Meeting with Human
Service to discuss planning for future
sidewalk locations (2-5 year plan). |
Rob Phelan |
|
6002 |
Human Services Sidewalks
2009-2010 projects |
04/20/10 - Page Park, Palmona Park and
Charleston Park sidewalk plans completed and
out for construction. Support as required. |
Rob Phelan |
|
6002 |
Human Services Sidewalks
2010-2011 projects |
04/20/10 - Pine Manor To review
preliminary locations identified for 2010-2011
plans |
Rob Phelan |
|
4723 |
Imperial Marsh Preserve
Wetland and Panther Mitigation Area Corkscrew
Mitigation. |
06/16/10 No change Exotic
Maintenance and monitoring ongoing. |
Betsie
Hiatt |
|
4060 |
Imperial Street 4-Laning
from Bonita Beach Road to E. Terry Street  |
Under Construction |
Nicole Maxey |
|
8546 |
Island Park Addition |
06/16/10 No Change - Purchase Contract denied |
Betsie
Hiatt |
|
8546 |
Island
Park Regional Mitigation Project (North and
South).
 |
06/16/10 - Construction for
North and South Phases complete. Monitoring
and maintenance ongoing. Additional contract
needed for South Phase maintenance. |
Betsie
Hiatt |
|
6674 |
Joel Blvd. at Country Club
- Left turn lane. |
06/16/10 Project completed. |
Sarah
Clarke |
|
6713 |
Lee Blvd. & Leonard Blvd. |
04/15/09 U-Turn location
shown on Concept Plans from Traffic at
Driveway location of proposed City of Fort
Myers development. Recommend not progressing
this project. |
Rob Phelan |
|
6713 |
Lee Blvd. / Sunshine Blvd.
Turn Lanes. |
06/15/10 - No Change, Under
Construction |
Eyra Cash |
|
6713 |
Leland Heights Blvd. / Lee
Blvd. |
06/16/10 - No change,
Preparing preliminary design for minor
intersection improvements |
Rob Phelan |
|
0700 |
Littleton Extension. |
04/15/08 Project completed. |
Sarah
Clarke |
|
6002 |
Littleton SidewalkOld 41
to US 41. |
06/15/10 - No Change, Under Construction |
Eyra Cash |
|
5060 |
Luckett / Sunshine Blvd.
Corridor Extension Studies. |
06/16/10 No Change, Final report complete. |
Sarah
Clarke |
|
5714 |
Master Bridge |
|
Ehab Guirguis |
|
|
Mitigation
Bank Permit |
06/16/10
application nearly complete / submittal
pending Corps guidance. |
Betsie
Hiatt |
|
5904 |
Matlacha Bridge
Replacement. |
04/20/10 - Plans Complete.
Award to BoCC 5/18/2010 |
Don
DeBerry |
|
|
Matlacha / Snook Inn bat
houses |
06/16/10 - DEP permit
issued. Bat houses complete and ready to be
installed. |
Betsie
Hiatt |
|
0700 |
N. Airport Rd. Extension. |
06/16/10 No Change, Discussion with developer have
resumed. Agreement is under review. |
Sarah
Clarke |
|
|
Neal Rd. paved shoulders
|
04/20/10 - No
change,
100% plans in house. |
Don
DeBerry |
|
4007 |
Orchid Isles ROMA. |
06/16/10 - No change,
Evaluation phase. |
Betsie
Hiatt |
|
|
Oriole Road.
 |
04/21/10 - DOS2008-00010, equivalent to 60
percent plans, is approved with stipulations.
Right-of-way dedication has not occurred.
Construction clearing and grubbing has
started. Administration performed by
developer. |
Andy Getch |
|
4072 |
Ortiz Avenue 4-Laning from SR 82 to SR 80
(Luckett Road).
 |
06/15/10 - No change, SFWMD permit approved, & working on
100% plans. |
Eyra Cash |
|
|
Ospreys / Sanibel Causeway |
06/16/10 poles installed / nest relocation
pending |
|
|
4007 |
Panther Fencing. |
7/15/08 No change,
Completed. Large female panther photographed
in crossing. |
Betsie
Hiatt |
|
4007 |
Panther Mitigation Area
(Sec. 33). |
06/16/10 Construction contract and
Utilities agreement pending. |
Betsie
Hiatt |
|
5722 |
Persimmon Ridge Bridge |
12/17/09 - Construction Complete |
Don
DeBerry |
|
4007 |
Pine Ridge Facility. |
06/16/10 No change, in
permitting / 2.13 mitigation credits will be
provided at Island Park |
Betsie
Hiatt |
|
4065 |
Plantation
Extension from Idlewild to Colonial Blvd.
 |
11/16/09 - Construction Complete
Opened
Nov. 13 |
Mike
Rigsby |
|
TBD |
Pondella Medians. |
06/16/10 No Change, Looking at median locations for
Pondella Road. |
Rob Phelan |
|
|
Red Sox Facility |
06/16/10 Permits issued, 1.8 credits at
Island Park |
Betsie
Hiatt |
|
6024 |
Roadway Beautification
Projects |
|
Pat Moore |
|
4084 |
Sandy Lane Design. |
04/21/10 - Project is not
funded in the current CIP |
Andy Getch
|
|
4084 |
Sandy Lane Extension |
03/16/09 -
No change, Project is not funded in the
current CIP |
Andy Getch |
|
|
Sanibel Causeway |
06/16/10 - permit issued for permit
modification / mitigation requirement. |
Betsie
Hiatt |
|
TBD |
Sanibel Causeway U-Turn |
04/21/09 - U-turn east of Toll Plaza
incorporated into TYLin Plans to be included
in Stimulus plans at Toll Plaza. |
Rob Phelan |
|
4604 |
Six Mile Cypress Parkway |
06/16/10 -
Bids Due 6/16/2010
LCU relocating water/sewer lines. City of
Fort Myers advertising water line adjustments |
Rob Phelan |
|
6002 |
Six Mile Cypress Pathway
Daniels to Metro Pkwy.  |
07/21/09 Construction Complete |
Sarah
Clarke |
|
6002 |
Six Mile Cypress Pathway
Metro to US 41. |
07/21/09 Construction Complete |
Sarah
Clarke |
|
6713 |
Six Mile Cypress Pkwy. &
Independence Circle W. |
08/18/09 Construction is complete. |
Lora Celec |
|
|
Slater Rd. paved shoulders
|
04/20/10 - 90% plans in house |
Don
DeBerry |
|
6002 |
Slater Rd. sidewalk
Bayshore to Del Prado Blvd. |
04/20/10 Construction Complete |
Sarah
Clarke |
|
5064 |
SR 82 / Daniels Dual
Left-Turn Lane. |
05/19/09 Construction Completed. |
Eyra Cash |
|
6002 |
Stringfellow Rd.
Sidewalk 1st Ave. to York Rd. |
06/15/10 No Change, Design in house |
Eyra Cash |
|
6007 |
Summerlin Rd. Cypress
Lake to
Boy Scout Drive.
 |
06/16/10 No Change, Under construction. |
Sarah
Clarke |
4067
|
Summerlin Road Sidewalk from
San Carlos Blvd. to Gladiolus Dr.  |
06/15/10 - 90% complete, being revised .
|
Mike
Rigsby |
|
4067 |
Summerlin Road Sidewalk
from Lakewood to Gladiolus Dr. |
11/16/09 - Construction Complete |
Eyra Cash |
|
4604 |
Sunniland Blvd Lee Blvd
to Park St. |
06/16/10 - No Change, Updating Plans for potential ARRA
Stimulus Funding. |
Rob Phelan |
|
6713 |
Sunshine Blvd. & 12th St. West |
12/17/09 - Construction Completed. |
Rob Phelan |
|
6002 |
Texas Rd. sidewalk
Leeland Hgts. To Davis. |
07/21/09 Construction Completed. |
Sarah
Clarke |
|
4053 |
Three
Oaks North from Alico to Airport Ditch
(Source, Inc.).
 |
04/21/10 - Project is substantially complete
for construction under DOS2005-00314.
Administration performed by developer.
Contractor is addressing punch list items. |
Andy Getch |
|
|
Three Oaks Park Rehab. |
04/20/10 - No change, Under Construction. |
Don
DeBerry |
|
4053 |
Three
Oaks Parkway From
Alico Canal to Daniels Parkway
 |
06/15/10 - No Change, Consultant submitted RAI to SFWMD,
working on 90% plans. |
Eyra Cash |
|
4043 |
Three Oaks Parkway South
from Brooks to E. Terry Street
 |
Under Construction. |
Nicole Maxey |
|
4081 |
Three Oaks Parkway Widening
from Corkscrew to Alico Rd.
 |
Under Construction. |
Nicole Maxey |
4081/
5021 |
Three Oaks Widening and
Estero Pkwy Wetland Mitigation |
Under Construction. |
Betsie
Hiatt |
|
6002 |
Tice St. sidewalk Ortiz
to Lexington. |
04/15/08 No change construction
nearing completion. |
Sarah
Clarke |
|
6002 |
Tice St. sidewalk Waverly
to Ortiz. |
04/15/08 Record plans received. Project
Completed. |
Sarah
Clarke |
|
|
Treeline Ave |
02/02/09 - Drafting Technical assistance
letter for panther signs and speed limits. |
Betsie
Hiatt |
|
TBD |
Veterans Pkwy. Merge lane
at Santa Barbara |
04/21/09 Provided sketch, estimate and
issues with merge lane to Scott. It is to be
discussed at COCC TAC meeting 1/29/09. |
Rob Phelan |
|
5020 |
Veteran's Pkwy. Mitigation
Area. |
06/16/10 Deed to state DEP pending BoCC
approval. Final exotic removal complete. |
Betsie
Hiatt |
|
5029 |
Veteran's Pkwy. Ramp |
04/15/08 Construction Completed. |
Sarah
Clarke |
|
Misc. |
Veterans Pkwy Right of Way |
06/16/10 - Researching
for ROW information for Cooner &
Associates |
Rob Phelan |
|
|
Veteran's / Surfside
Intersection |
|
Don
DeBerry |
|
6755 |
Veterans Pkwy./Santa Barbara Overpass |
6/16/10 Design project kick off held June 3,
2010. |
Sarah
Clarke |
|
4007 |
Wake / Hatchee |
6/16/10 Permitting complete |
Betsie
Hiatt |
|
4007 |
Wild Turkey Strand Wetlands
and Panther Mitigation Area |
06/16/10 In permitting. Additional topo
pending. Ditch crossing permit issued for P&R. |
Betsie
Hiatt |
|
6675 |
Williams Rd. at 5th
St. left turn lane. |
11/17/09 No Change, Under Construction. |
Sarah
Clarke |
|
6002 |
Williams Road Sidewalk.
 |
05/19/09 Construction Completed. |
Eyra Cash |
|
Misc. |
Winker Road / College Parkway ROW Vacation |
06/16/10 - Working with utilities to
identify (LCU / Embarq) to identify objection
to ROW vacation
Partial vacation of Zipperer deed by
applicant completed. |
Rob Phelan |
|
|
|
|
Elderberry Lane. |
08/18/09 - Road open |
Mike
Rigsby |
|
|
MSBU San Carlos Dr. |
6/16/10 San Carlos Dr. project under
construction. |
Sarah
Clarke |
|
|
MSBU Western Acres,
Harbor Dr., Homestead Ln., San Carlos Dr. |
4/20/10 San Carlos Dr. project under
construction. |
Sarah
Clarke |
|
|
Roundabouts on Sunshine &
23rd . |
04/20/10 - No
Change, 8th St
needs right of way |
Don
DeBerry |
|
|
|
|
|
|
Advertise: |
|
|
|
|
951 / Golf Course
Maintenance Swap |
01/29/09 - Ranking approved by BoCC 4/15/2008
will begin negotiating contracts. |
Don
DeBerry |
|
|
Orange River Paved
Shoulders |
04/20/10 - No Change, 100% plans in house |
Don
DeBerry |
|
|
Palmetto Ridge Bridge
Replacement |
01/29/09 - Selected consultants. |
Don
DeBerry |
|
|
|
|
|